More First Fix Details

Feb. 13: There are always several trades working alongside the Zebra carpenters. Progress now is measured in details, and the following images demonstrate some of those details that were evident this week. 

As noted before, each window and door is custom framed in cedar prior to installation of the cedar siding. this is the West side of the house. 

As noted before, each window and door is custom framed in cedar prior to installation of the cedar siding. this is the West side of the house. 

East side of the house with the kitchen windows and mudroom door framed in cedar.

East side of the house with the kitchen windows and mudroom door framed in cedar.

Martin and Bob measuring for a small access door between the mechanical room and the crawl space (which we can use as storage). Bob is supplying the interior doors (all 24) throughout the house.

Martin and Bob measuring for a small access door between the mechanical room and the crawl space (which we can use as storage). Bob is supplying the interior doors (all 24) throughout the house.

Gas pipes in the mechanical room

Gas pipes in the mechanical room

Piping detail behind the holding tank.

Piping detail behind the holding tank.

Roughing-in the drop ceiling in the walk-in closet - this is necessary to house the A/C venting. 

Roughing-in the drop ceiling in the walk-in closet - this is necessary to house the A/C venting. 

Finishing the rough-in for the elevator.

Finishing the rough-in for the elevator.

The dog/utility shower base...

The dog/utility shower base...

View from the Master bedroom - this is why we are doing this! I love this view!!!